Work on a consistent wet basis
Wet-basis moisture is water mass divided by total product mass. Use the same basis for starting and final moisture.
PROCESS ENGINEERING
Estimate dry output and water removal from fresh input and wet-basis moisture.
ENGINEERING GUIDE
Wet-basis moisture is water mass divided by total product mass. Use the same basis for starting and final moisture.
Assuming solids are conserved, divide dry solids by one minus the target moisture fraction to estimate dried product. Subtract that mass from fresh input for theoretical water removal.
For continuous production, use an hourly basis. For a batch, a cycle average needs the full cycle and turnaround time. Include cutting loss and downtime separately.
CAPACITY PLANNING
Estimate a mass balance with the moisture data for your own raw material.